Soul City Solar has submitted its Conditional Use Permit (CUP) application to Hinds County for both the solar and energy storage portions of the project on April 30, 2024. Below is a brief timeline of the local permitting process and links to materials

  • April 29, 2024 - Public notice of application mailed to all property owners within 300 feet of project boundary and published in local newspapers
  • April 30, 2024 - Conditional Use Permit Applications submitted to Hinds County

  • May 14, 2024 - Soul City Solar Open House and Community Information Session at McKenzie Arena in Raymond

  • May 22, 2024 - Supplement to application with information in response to the May 14th community meeting submitted to Hinds County Building Department

  • May 28, 2024 - Hinds County Planning Commission Public Hearing (Public Notice as published on May 9, 2024 in Jackson Advocate and Clarion Ledger)

  • June 17, 2024 - Hinds County Board of Supervisors Review of Application

Select application materials are linked below for your reference:

May 14, 2024 Community Information Meeting Materials

Soul City Solar (Energy) Conditional User Permit Submissions

Soul City Storage Conditional User Permit Submissions

Revised Site Plan (May 22, 2024 Supplemental):